Project Details

Contractor / Owner
Kitchell ContractorsKitchell Contractors
Services
Surface Demolition & Removals
Soil Nailing
Land Clearing & Grubbing
Site Work / Site Development
Shotcrete Finish Walls
Dust Control
Mass Excavation
Shoring / Earth Retention
Shotcrete
Market
Healthcare
Location
Phoenix, Arizona
Completion Date
2009

Project Description

Phoenix Children's Hospital – Patient Care Tower & Central Plant is an extension to the current facility located in the heart of Phoenix, Arizona.  Buesing Corp. was contracted for both the below-grade excavation and shoring.  The project included many challenging design requirements in a tight working environment.

  • 60,000 cubic yards of excavation and haul off
  • 30,000 square feet of soil nail shoring
  • 1,500 square feet of shotcrete finish wall at the Central Plant

Images