Project Details

Contractor / Owner
The Opus GroupThe Opus Group
Services
Surface Demolition & Removals
Aggregates
Land Clearing & Grubbing
Steel Beam & Lagging
Site Work / Site Development
Import / Export Soil
Material Transportation / Trucking Services
Shotcrete Finish Walls
Dust Control
Mass Excavation
Shoring / Earth Retention
Shotcrete
Site Cut / Fill
Foundation Drilling
Structural Excavation & Backfill
Backfill / Embankment Fill
Market
Commercial / Retail
Location
Tempe, Arizona
Completion Date
2009

Project Description

Tempe Gateway is one of the newest high-rise additions to the very popular Mill Ave District in Tempe, Arizona. Buesing Corp. was contracted for the installation of shoring and excavation. A cantilever steel beam shoring system was used to protect the recently installed light rail system and utilities adjacent to the underground garage.

  • 25,000 cubic yards of excavation and haul off
  • 13,000 square feet of cantilevered steel beam shoring
  • 200,000 pounds in wide flange beams used