The Madison School needed more parking capacity and a below grade garage was the solution. Team Buesing delivered the shoring and mass excavation to help the GC deliver this project while working around the school’s schedule.
The Buesing Advantage - Team Buesing’s ability to deliver a turn key below grade facility give the General Contractor the freedom to focus on the vertical components of the structure without having to coordinate between individual shoring and excavation trades. Buesing’s ability to deliver all possible types of shoring makes budgeting easier because we can change systems to fit each part of the hole if necessary.
Location
Phoenix, AZ
Owner
Core Construction (GC)
General Contractor
Project Duration
2017 - 2018
Services
- Earth Retention Shoring
- Site Work
Deliverables
- Site removals
- 22,000 SF Design-Build Temp Shoring
- 30,000 CY Mass Excavation and Export
- Site Grading