Project Description

The Copper Crossing Solar Plant project is located on 144 acres of former private agricultural land in Pinal County, Arizona. The project will have an overall capacity of 17MW and will be constructed in phases, with Phase I generating 5MW. Buesing Corp.'s scope of work involved the site preparation of the construction trailer area and roadway entrances to the site and the installation of the first phase of piles for the photo-voltaic solar panels.

  • Installation of 3,096 piles
  • Piles of lengths of 12' and 14'
  • Piles set at depths of 6.5 feet and 8.5 feet